The letter Mahagenco wrote to WCL in June, stated that Mahagenco's 2,880 MW units including Parli, Bhuswal and Paras TPS were completely under reserve shut down and therefore the CIL subsidiary was requested to supply 10.5 rakes of coal a day instead of the programmed 22.7 rakes a day, a reduction of above 50% of the programme.