In a bid to provide relief to renewable energy players, the government has allowed the implementing agencies to extend the commissioning date of solar PV and solar PV-wind hybrid power projects till March 31, 2024.
"Solar PV power developers/associations have represented to MNRE that there is a supply chain disruption in the solar PV sector and have requested appropriate reliefs to tackle the same," the Ministry of New and Renewable Energy (MNRE) said in a notification on Thursday.
"This issue has been examined in the Ministry and it has been decided that implementing agencies SECI/NTPC/NHPC may extend the scheduled commissioning date (SCD) till 31.03.2024 and commensurately extend other associated intermediate milestones of such solar PV/Solar PV-wind hybrid power projects, wherein the last date of bid submission was on or after 10.04.2021 and whose SCD, including time-extensions, already granted, if any, is before 31.03.2024, and who wish to avail such time-extension," it said.
Th